Height: Occupied
87.2 m / 286 ft
 
Height: To Tip
110 m / 361 ft
Height: Architectural
110 m / 361 ft
 
Edith Green-Wendell Wyatt Federal Building Outline
Floors Above Ground
18
Floors Below Ground
2
# of Elevators
7
Tower GFA
48,774 m² / 524,999 ft²
Development GFA
48,774 m² / 524,999 ft²
# of Parking Spaces
184

Facts

Official Name Edith Green-Wendell Wyatt Federal Building
Other Names EGWW Federal Building
Structure Type Building
Status Completed
Country United States
City Portland
Street Address & Map 1220 SW 3rd Avenue
Postal Code 97201
Building Function office
Structural Material steel
Proposed 2003
Construction Start 2010
Completion 2013
Official Website Edith Green-Wendell Wyatt Federal Building

Companies Involved

Owner General Services Administration
Architect
Design Cutler Anderson Architects
Architect of Record SERA Architects
Structural Engineer
Design KPFF Consulting Engineers
MEP Engineer
Design Interface; PAE Consulting Engineers; Stantec Ltd.
Main Contractor Howard S Wright Construction
Other Consultant
• Acoustics Acoustic Design Studio; Charles M. Salter Associates
• Landscape PLACE
Material Supplier
• Cladding Benson Industries

About Edith Green-Wendell Wyatt Federal Building

The Edith Green-Wendell Wyatt (EGWW) Federal Building is an office tower, completed in 1974. The building no longer met the functional or the energy and conservation requirements of the contemporary US government, so a major renovation project was undertaken. A mechanical upgrade, seismic retrofit, and full interior rehabilitation was paired with a full replacement of the building envelope with a distinctive shading facade, affording better energy performance and a new lease on life.

While investigating the brief, the architects discovered that the existing concrete skin of the structure covered up to 600 millimeters of floor area for every 300 lineal millimeters of exterior wall. By applying a new skin to the existing slab edges and making other changes related to HVAC systems, the design added 9,449 square meters of new rentable office space, which amortized the added cost of the envelope. About 650 square meters of that space was freed up by switching to water cooling, which reduced the building’s thermal load to the point that the large fans for the previous forced-air cooling system could be removed. Additionally, removing the concrete façade panels simplified the seismic retrofit of the building due to the reduction of weight; the new façade system could be attached to the structural frame with a series of relatively short steel beams.

Because of the importance daylighting plays in human health and comfort, the project optimized solar penetration in the perimeter zone by deploying a low-powered ambient lighting in concert with focused task lamps. This resulted in a 50-to-60 percent reduction in energy consumption for lighting, while providing occupants with a valuable connection to the outdoors. The depth and spacing of the shading devices were varied to arrive at the performance metrics the designers used to derive the building’s aesthetic expression.

In order to respond to the unique solar exposure of the site, each face of the building was designed to both shade direct solar gain and reflect light into the interior spaces to enhance day-lighting. The result was a building that presents a different face to each solar circumstance. The reed-like shades affixed to the sides of the building are tuned for each facade to reduce solar gain, and a 3,962 square-meter roof canopy supports a 180 kW photovoltaic array, while also collecting rainwater.

Greater than 65 percent water savings will be achieved through a dual strategy of incorporating-water conserving plumbing fixtures together with a rainwater system. The water conservation strategy started with an analysis of how the existing building used water. Eighty-seven percent of the building’s water usage is for domestic uses, with 13 percent used for irrigation of surrounding vegetation. Because of this large interior use, the strategy focused on reusing rainwater for non-potable flush fixture uses first. Landscape water use is reduced by over 50 percent as well, through use of drought-resistant landscaping and incorporation of subsurface irrigation.

A 624,593-liter tank, created by repurposing an old rifle range, allows rainwater to be stored and used for toilet flushing, irrigation, and mechanical cooling tower makeup water. The tank also supports another project goal: mitigating the negative effects of urban runoff. Ultimately, the EGWW building is expected to save over 7.5 million liters of water annually – enough water to fill 22 swimming pools.

EGWW is designed to achieve a 60 percent reduction in energy use compared to the existing building, and a reduction of Energy Use Intensity (EUI) by 45 percent. A large portion of those savings will come from having eliminated forced-air fans.

These savings are the result of an integrated design process that prioritized comfort for the occupants and energy performance. Exterior shading, tuned by facade orientation, provides solar control while enhancing daylighting, thereby minimizing cooling load and peak electric load, and improving thermal comfort. These integrated strategies allowed the prime energy conservation measure, a radiant ceiling heating and cooling system, to be realized. Additionally, the building program was tuned to optimize performance with an ideal plan optimized at 70 percent open offices and 30 percent closed offices, provided for each agency. Common areas were moved toward windows, and interior walls were changed to glass to admit more light.

Videos

A Model Modernization: Edith Green-Wendell Wyatt Federal Building and GSA’s Mid-Century Inventory
26 Oct 2015 – Leslie Shepherd, General Services Administration

2014 Awards - Session 3 Q&A
6 Nov 2014 – Chair: Antony Wood, Executive Director, CTBUH

Best Tall Building Americas: Concrete Monolith to Green Machine: Edith Green-Wendell Wyatt Federal Building
6 Nov 2014 – Leslie Shepherd, General Services Administration; James Cutler, Cutler Anderson Architects

More Videos

Videos Related to Edith Green-Wendell Wyatt Federal Building

Videos Related to Edith Green-Wendell Wyatt Federal Building

A Model Modernization: Edith Green-Wendell Wyatt Federal Building and GSA’s Mid-Century Inventory
26 Oct 2015 – Presentation at CTBUH 2015 New York Conference; Leslie Shepherd, General Services Administration
Edith Green-Wendell Wyatt Federal Building (EGWW) is an 18-story federal office designed by Skidmore, Owings & Merrill and constructed in downtown Portland, Oregon, in…
2014 Awards - Session 3 Q&A
6 Nov 2014 – CTBUH "13th Annual Awards"; Chair: Antony Wood, Executive Director, CTBUH
Thursday, 6th November 2014 Chicago, USA. Leslie Shepherd, Chief Architect, General Services Administration, James Cutler, Founding Partner, Cutler Anderson Architects,…
Best Tall Building Americas: Concrete Monolith to Green Machine: Edith Green-Wendell Wyatt Federal Building
6 Nov 2014 – CTBUH "13th Annual Awards"; Leslie Shepherd, General Services Administration; James Cutler, Cutler Anderson Architects
The Edith Green-Wendell Wyatt (EGWW) Federal Building is an office tower, completed in 1974. The building no longer met the functional or the energy and conservation…
CTBUH 13th Annual Awards Dinner
6 Nov 2014 – CTBUH "13th Annual Awards"; Dinner 2014
The 13th Annual Awards Ceremony & Dinner was held in Mies van der Rohe's iconic Crown Hall, on the Illinois Institute of Technology campus, Chicago. The 13th Annual CTBUH…
Interview: Edith Green-Wendell Wyatt Federal Building
6 Nov 2014 – 2014 Awards Ceremony/Symposium Interviews; Leslie Shepherd, General Services Administration; James Cutler, Cutler Anderson Architects
Thursday 6th November 2014. Chicago, IL. Leslie Sheppard, General Services Administration, and Jim Cutler, Cutler Anderson Architects, are interviewed by Chris Bentley…

Browse hundreds of other videos from Council events including conferences and interviews with prominent tall building professionals in the Video Library

Research Papers

A Model Modernization: Edith Green-Wendell Wyatt Federal Building and GSA’s Mid-Century Inventory
26 Oct 2015 – Global Interchanges: Resurgence of the Skyscraper City

CTBUH Awards

Best Tall Building Americas 2014 Winner
CTBUH Awards 2014


To submit more information or donate images for this project, please use our submission portal.